You lead supply chain planning for a component manufacturer. Choose the business goal and see how the same evidence leads to different actions. All figures are synthetic.
What the evidence says
Part A has 60 usable units against a confirmed order for 100 due Friday. Its next receipt is Monday, and expediting 40 units costs ₹12,000. Part B has 240 units against a 60-unit four-week forecast and another 100 due next week.
Confirm supplier capacity, usable stock and whether the customer accepts split delivery. The Part B forecast may change.
What the manager weighs
Expedite the Part A shortage, negotiate split delivery, or reschedule the Part B receipt. Compare service risk, cash tied up and the effect of freight on order margin.
The supply chain lead owns the decision with sales and finance input.